Port owner | Size/Ship types | OPS | New OPS – future plans | OPS established |
ADP A/S ((Ports of Fredericia and Nyborg) | Small- and supply ships | 63 -125A | Looking at the possibilities of shore power to ro-ro | 2021--- |
CMP (Copenhagen -Malmø Port) | no info | Planning to supply ferries to Oslo | 2021-- | |
Esbjerg | All ships, supply ships, offshore rigs etc. | 2 units that can supply up to 10.000 kW, 500 A and 50/60H | Planning new on shore power supply for supply ships | 2021 |
Frederikshavn | All ships | Have supplied up to 800A in cooperation with local energy supply company | All ships | |
Grenå | All ships, (ships which have been maintained for a long time or are stored in the port of Grenaa) | Have a mobile OPS, that can supply up to 2000 kW mobile power unit 50/60Hz (Powercon) | 2019 | |
Hanstholm | Small – medium fishing ships Automatic power supply | 125A | A new quay in 2020 | |
Helsingør | Ferries | 640 batteries of 6.5 kWh | Onshore power for battery ferries, 640 batteries of 6.5 kWh. Charged with 1,200 kWh each time the ferries are in port. charged with approximately 1,200 kWh each time the ferries are in port. | 2018 |
Hirtshals | Small – medium fishing ships | 63-125A | Looking at the possibilities of shore power to bigger pelagic fishing ships | 2021 --- |
Hvidesande | Small ships- fishing ships | 63A | Looking at the possibilities for hydrogen supply for dredging ships. | 2019--- |
Kalundborg | Small ships | 63- 125A | All ships | |
Kolding | Small ships | 63A | The port of Kolding is looking at the possibilities for a new OPS for cargo ships (container, bulk etc) | 2021 --- |
Køge | All ships | 10-125 A | ||
Randers | Small ships | 32 A -63A | All ships (can only support small ships) | |
Rønne | Up to 400A | Bornholmslinien from Rønne - Køge are investigating OPS for the ferrys | 2021-- | |
Skagen | Small – medium fishing ships | 350A in new quays 125A in old ones. Automatic power supply for fishing ships | 10 pcs. 350A to supply 10 ships with different voltage levels and frequencies, independently of each other. Each outlet can supply voltages from 400V to 690V with 50Hz or 60Hz | October 2021 |
Thyborøn | Small – medium fishing ships | Normal 63 -125A but can supply up to 350A | Thyborøn are seeking funds for OPS up to 800A for bigger ships (supply ships – drilling rigs etc). | 2021 -- |
Aabenraa | Small ships | 63A | All ships (can only support small ships) | |
Aarhus | Ferries | Planning supply 4 ferries, each at 300 KW | Have power supply for tugs. | 2021 |